Purchasing
Live144 to decide0 of 144 decided, 144 to go. 66 of those run out before their supplier could deliver, so they are at the top. £156,207 of buying is proposed and 54 lines can be covered by moving stock the group already owns.
- 8383 lines have been waiting a week or moreThe oldest has sat here 15 days. Nothing on a queue announces itself, so the platform counts the days and puts them in front of you.Show these
- 1515 lines have no lead time on their supplier recordFourteen days is assumed on those lines and the confidence is marked down to say so. The assumption is on the line, never hidden inside the figure.Show these
- 2222 lines sit under their supplier minimum on their ownEach one is combined onto that supplier's draft order rather than shipped alone, so the minimum is met and carriage is not paid twice.Showing these
- 2222 lines carry a one-off monthA mobilisation or a contract pause is excluded from the forecast rather than left to inflate the next order. The exclusion is stated on the line so a buyer can disagree with it.Show these

MSC West — Feltham holds 16 free, which is 2 days of cover against a forecast of 7.2 a day. Robert Scott needs 10 days and class A carries 7 days of safety stock, so the target position is 123 units. MSC East — Brentwood can release 89, so move 89 first and buy the remaining 20 from Robert Scott.
Do nothing and MSC West — Feltham runs out on 29/08/2026, which is 2 days. Robert Scott needs 10 days to deliver. That is about £1,261 of sales at risk on this line alone.
Transfer first: MSC East — Brentwood can release 89 without dropping below its own cover. Moving 89 arrives next day on the trunk run for £13.42 of handling, holds back £855 of spend and avoids 1.9 kg CO2e.

MSC West — Feltham holds 0 free, which is under a day of cover against a forecast of 8.9 a day. Robert Scott needs 10 days and class A carries 7 days of safety stock, so the target position is 152 units. MSC East — Brentwood can release 101, so move 101 first and buy the remaining 54 from Robert Scott.
Do nothing and MSC West — Feltham is already out, so every order for this line goes short until something arrives. That is about 89 units of demand across the lead time. That is about £597 of sales at risk on this line alone.
Transfer first: MSC East — Brentwood can release 101 without dropping below its own cover. Moving 101 arrives next day on the trunk run for £9.03 of handling, holds back £399 of spend and avoids 0 kg CO2e.
MSC West — Feltham holds 0 free, which is under a day of cover against a forecast of 7.9 a day. Portwest Clothing needs 18 days and class B carries 10 days of safety stock, so the target position is 221 units. Neither depot has spare cover, so buy 230 from Portwest Clothing.
Do nothing and MSC West — Feltham is already out, so every order for this line goes short until something arrives. That is about 142 units of demand across the lead time. That is about £265 of sales at risk on this line alone.

MSC West — Feltham holds 6 free with 25 already inbound, which is 10 days of cover against a forecast of 3.1 a day. Bio Productions needs 5 days and class A carries 7 days of safety stock, so the target position is 38 units. Neither depot has spare cover, so buy 12 from Bio Productions.
Do nothing and MSC West — Feltham runs out on 29/08/2026, which is 2 days. Bio Productions needs 5 days to deliver. That is about £198 of sales at risk on this line alone.

MSC West — Feltham holds 0 free with 47 already inbound, which is 5 days of cover against a forecast of 10.4 a day. Bio Hygiene needs 3 days and class A carries 7 days of safety stock, so the target position is 104 units. Neither depot has spare cover, so buy 60 from Bio Hygiene.
Do nothing and MSC West — Feltham is already out, so every order for this line goes short until something arrives. That is about 31 units of demand across the lead time. That is about £140 of sales at risk on this line alone.

MSC East — Brentwood holds 0 free, which is under a day of cover against a forecast of 0.8 a day. Bio Hygiene needs 3 days and class C carries 14 days of safety stock, so the target position is 15 units. Neither depot has spare cover, so buy 20 from Bio Hygiene.
Do nothing and MSC East — Brentwood is already out, so every order for this line goes short until something arrives. That is about 3 units of demand across the lead time. That is about £10 of sales at risk on this line alone.

MSC East — Brentwood holds 58 free, which is 11 days of cover against a forecast of 5.3 a day. Supermax Healthcare needs 12 days and class A carries 7 days of safety stock, so the target position is 101 units. Neither depot has spare cover, so buy 50 from Supermax Healthcare.
Do nothing and MSC East — Brentwood runs out on 07/09/2026, which is 11 days. Supermax Healthcare needs 12 days to deliver. That is about £1,138 of sales at risk on this line alone.

MSC East — Brentwood holds 54 free with 43 already inbound, which is 18 days of cover against a forecast of 5.3 a day. Northwood Hygiene Products needs 12 days and class A carries 7 days of safety stock, so the target position is 101 units. Neither depot has spare cover, so buy 6 from Northwood Hygiene Products.
Do nothing and MSC East — Brentwood runs out on 06/09/2026, which is 10 days. Northwood Hygiene Products needs 12 days to deliver. That is about £637 of sales at risk on this line alone.
Products, suppliers, prices and case multiples are MSC's real range. Demand history, lead times and supplier terms are derived for the demo, deterministically, so the figures never move between screens. An asterisk on a lead time means the supplier record carries none and fourteen days was assumed, the same gap the audit found on about 19,900 SKUs. Signed in as Duncan Cusack.