Jangro Blue Nitrile Gloves Medium 100 Pack - DG150‑M
LiveWatch
MSC East — Brentwood holds 58 free, which is 11 days of cover against a forecast of 5.3 a day. Supermax Healthcare needs 12 days and class A carries 7 days of safety stock, so the target position is 101 units. Neither depot has spare cover, so buy 50 from Supermax Healthcare.
Do nothing and MSC East — Brentwood runs out on 07/09/2026, which is 11 days. Supermax Healthcare needs 12 days to deliver. That is about £1,138 of sales at risk on this line alone.
| Step | Why | Units |
|---|---|---|
| Free stock at the depot | 67 on hand less 9 already allocated to orders | 58 |
| Open purchase orders inbound | Nothing on the water | 0 |
| Position the engine works from | Free stock plus what is already inbound | 58 |
| Forecast demand a day | Eight weeks ahead, seasonally shaped, one-off months excluded | 5.27 |
| Lead-time demand | 5.27 a day for 12 days from Supermax Healthcare | 64 |
| Safety stock, class A | Class A carries 7 days of cover for the variability this line shows | 37 |
| Target position | Lead-time demand plus safety stock | 101 |
| Shortfall | Target position less the position now, which is why this line is on the queue | 43 |
| Rounded to the supplier multiple | Supermax Healthcare ships in cases of 10 | 50 |
MSC West — Feltham holds 0 free and needs all of it for its own cover, so there is nothing to move.
- Order50 units, 5 cases of 10
- ArrivesDay 12
- Cost£495.00, carriage paid
- Terms45 days net · Supplier portal
- Supplier record84 per cent on time, 93 per cent in full
- Minimum order£500, so this line is combined onto the supplier's order rather than shipped alone
Products, suppliers, prices and case multiples are MSC's real range. Demand history, lead times and supplier terms are derived for the demo, deterministically, so the figures never move between screens.