Purchasing
Live144 to decide0 of 144 decided, 144 to go. 66 of those run out before their supplier could deliver, so they are at the top. £156,207 of buying is proposed and 54 lines can be covered by moving stock the group already owns.
- 8383 lines have been waiting a week or moreThe oldest has sat here 15 days. Nothing on a queue announces itself, so the platform counts the days and puts them in front of you.Show these
- 1515 lines have no lead time on their supplier recordFourteen days is assumed on those lines and the confidence is marked down to say so. The assumption is on the line, never hidden inside the figure.Show these
- 2222 lines sit under their supplier minimum on their ownEach one is combined onto that supplier's draft order rather than shipped alone, so the minimum is met and carriage is not paid twice.Show these
- 2222 lines carry a one-off monthA mobilisation or a contract pause is excluded from the forecast rather than left to inflate the next order. The exclusion is stated on the line so a buyer can disagree with it.Show these

MSC West — Feltham holds 46 free with 12 already inbound, which is 8 days of cover against a forecast of 7.2 a day. Polyco Healthline needs 3 days and class A carries 7 days of safety stock, so the target position is 72 units. Neither depot has spare cover, so buy 18 from Polyco Healthline.
Do nothing and MSC West — Feltham runs out on 02/09/2026, which is 6 days. Polyco Healthline needs 3 days to deliver. That is about £203 of sales at risk on this line alone.

MSC West — Feltham holds 26 free, which is 8 days of cover against a forecast of 3.2 a day. MSC Shop needs 6 days and class A carries 7 days of safety stock, so the target position is 42 units. Neither depot has spare cover, so buy 20 from MSC Shop.
Do nothing and MSC West — Feltham runs out on 04/09/2026, which is 8 days. MSC Shop needs 6 days to deliver. That is about £192 of sales at risk on this line alone.

MSC West — Feltham holds 2 free, which is 14 days of cover against a forecast of 0.1 a day. Numatic needs 8 days and class A carries 7 days of safety stock, so the target position is 3 units. Neither depot has spare cover, so buy 1 from Numatic.
Do nothing and MSC West — Feltham runs out on 10/09/2026, which is 14 days. Numatic needs 8 days to deliver. That is about £183 of sales at risk on this line alone.

MSC West — Feltham holds 68 free, which is 6 days of cover against a forecast of 11.0 a day. Bio Hygiene needs 3 days and class A carries 7 days of safety stock, so the target position is 110 units. Neither depot has spare cover, so buy 50 from Bio Hygiene.
Do nothing and MSC West — Feltham runs out on 02/09/2026, which is 6 days. Bio Hygiene needs 3 days to deliver. That is about £126 of sales at risk on this line alone.

MSC West — Feltham holds 28 free, which is 5 days of cover against a forecast of 5.5 a day. Bio Hygiene needs 3 days and class A carries 7 days of safety stock, so the target position is 55 units. Neither depot has spare cover, so buy 30 from Bio Hygiene.
Do nothing and MSC West — Feltham runs out on 01/09/2026, which is 5 days. Bio Hygiene needs 3 days to deliver. That is about £121 of sales at risk on this line alone.

MSC West — Feltham holds 26 free, which is 15 days of cover against a forecast of 1.7 a day. MSC Shop needs 6 days and class B carries 10 days of safety stock, so the target position is 28 units. MSC East — Brentwood can release 53 without going short, so move 2 on tomorrow's trunk run and buy nothing.
Do nothing and MSC West — Feltham runs out on 11/09/2026, which is 15 days. MSC Shop needs 6 days to deliver. That is about £104 of sales at risk on this line alone.
Transfer first: MSC East — Brentwood can release 53 without dropping below its own cover. Moving 2 arrives next day on the trunk run for £9.26 of handling, holds back £12 of spend and avoids 0.1 kg CO2e.

MSC West — Feltham holds 44 free, which is 7 days of cover against a forecast of 6.1 a day. Bio Hygiene needs 3 days and class A carries 7 days of safety stock, so the target position is 61 units. MSC East — Brentwood can release 147 without going short, so move 17 on tomorrow's trunk run and buy nothing.
Do nothing and MSC West — Feltham runs out on 03/09/2026, which is 7 days. Bio Hygiene needs 3 days to deliver. That is about £96 of sales at risk on this line alone.
Transfer first: MSC East — Brentwood can release 147 without dropping below its own cover. Moving 17 arrives next day on the trunk run for £12.68 of handling, holds back £53 of spend and avoids 1.6 kg CO2e.

MSC West — Feltham holds 102 free, which is 13 days of cover against a forecast of 7.7 a day. Harrison Wipes needs 6 days and class B carries 10 days of safety stock, so the target position is 123 units. MSC East — Brentwood can release 110 without going short, so move 21 on tomorrow's trunk run and buy nothing.
Do nothing and MSC West — Feltham runs out on 09/09/2026, which is 13 days. Harrison Wipes needs 6 days to deliver. That is about £67 of sales at risk on this line alone.
Transfer first: MSC East — Brentwood can release 110 without dropping below its own cover. Moving 21 arrives next day on the trunk run for £9.25 of handling, holds back £20 of spend and avoids 0.1 kg CO2e.
Products, suppliers, prices and case multiples are MSC's real range. Demand history, lead times and supplier terms are derived for the demo, deterministically, so the figures never move between screens. An asterisk on a lead time means the supplier record carries none and fourteen days was assumed, the same gap the audit found on about 19,900 SKUs. Signed in as Duncan Cusack.